HMCTS Willesden

Keeping a busy Magistrates’ Court fully operational while replacing its major building services presented exactly the type of challenge our team enjoys. Working at HMCTS Willesden, Prometheus delivered a comprehensive decarbonisation scheme replacing ageing gas boilers, chillers and ventilation plant with a modern, fully electric MEP solution.

The new installation combines Mitsubishi four-pipe Air Source Heat Pumps and Water Source Heat Pumps, with dedicated DX systems providing independent environmental control to the courtrooms. Ventilation serving the courtrooms and custody areas was also upgraded, while the new equipment was integrated into the existing Trend BMS to provide improved monitoring and control.

Of course, carrying out major works within a live judicial and custody environment brought its own challenges. Courtrooms, custody areas, judges’ chambers and public spaces remained in daily use, so disruptive activities were carefully planned around court sittings and undertaken out of hours. Through close coordination with court representatives and careful sequencing of the works, services were maintained and the project was delivered without disruption to court operations.