Blackburn Hospital – Critical Chiller Works

Maintaining critical cooling within a live hospital environment requires careful planning, particularly when essential plant needs to be replaced or has unexpectedly failed. At Blackburn Hospital, Prometheus undertook a series of chiller works where continuity of cooling was at the heart of the delivery strategy.

The works included the replacement of an existing CT chiller with a new Parker Hiross unit. To keep the system live throughout the replacement, a temporary chiller was introduced, allowing planned shutdowns and changeovers to be carefully scheduled to minimise the impact on hospital services.

When a separate chiller subsequently failed, Prometheus again provided temporary cooling to maintain the required supply. This required an electrical switchover together with modifications and diversions to the existing pipework to integrate the temporary chiller with the hospital’s systems.

Working within a live hospital meant disruption had to be kept to an absolute minimum. Through careful planning, temporary plant and coordinated shutdowns, Prometheus maintained cooling provision while both the planned replacement and responsive works were successfully undertaken.